OFFICE AREA
433m2
WAREHOUSE AREA
1700m2
BUILD DURATION
16 Months

CoolTranz

CoolTranz Distribution Warehouse & Offices - A Collaborative Design & Build Success Story

Project Overview:

This project involved the design and construction of a two-stage facility for CoolTranz in Hornby, Christchurch with a third stage currently under construction. The phased delivery of the project allowed CoolTranz to continue operations with minimal disruption. With an innovative approach to workplace design and dedication to creating a positive and productive work environment, the client's commitment to excellence has resulted in a truly exceptional facility that sets a new standard for industrial workplaces.

  • Stage 1: A 1700m² cool storage distribution center featuring eight loading docks, each equipped with sectional insulated doors, inflatable dock seals, and hydraulic dock levellers.
  • Stage 2: A purpose-built office building designed to prioritize comfort and functionality for staff and truck drivers. Stage 2 was constructed while working in a live environment so maintaining a safe work environment was paramount. This stage incorporated custom and architecturally designed elements including:
    • Fully tiled showers and bathrooms.
    • Hand crafted vanities.
    • Custom louver system.
    • Rendered concrete plaster finish.
    • Expertly crafted kitchen and recreation areas.
    • A steel art wall depicting the journey of CoolTranz in the design.
  • Stage 3: A fuel depot that is currently under construction.

Challenges Overcome:

  • Logistical Coordination: Coordinating the delivery of internationally sourced materials required careful planning and mitigation strategies to ensure timely completion.
  • Live Environment: Maintaining a safe working environment was paramount. Procore facilitated effective tracking and reporting of safety incidents and hazards.

Tools and Technologies:

  • Procore: This construction management software provided a platform for communication, collaboration, managing financials, invoices, and design coordination.
  • Last Planner System: This project management method facilitated collaborative task planning between trade contractors, project managers, and stakeholders, ensuring clear workflows, accountability, and improved project delivery.

Project Delivery Method:

  • Stage 1: 1700m2 Coolstore warehouse and truck wash, completed December 2023
  • Stage 2: 433m2 Office block, completed in October 2024
  • Stage 3 : Fuel depot, currently under construction

Conclusion:

This project is a testament to our collaborative approach, efficient project management practices, and commitment to client satisfaction. By combining innovative tools, teamwork, and meticulous design, we delivered a high-quality facility that exceeds CoolTranz's expectations and paves the way for their future expansion.

COHESIVE GROUP

Find out more about working on a building project with us

contact us
View on
Instagram
Floor bolt holding up large construction
View on
Instagram
Interior bathroom for Cohesive homes
View on
Instagram
Meeting room at Commercial Property
View on
Instagram
Cold pressed steel
View on
Instagram
Cohesive homes shed homes
View on
Instagram
Cohesive homes