CoolTranz Distribution Warehouse & Offices - A Collaborative Design & Build Success Story
Project Overview:
This project involved the design and construction of a two-stage facility for CoolTranz in Hornby, Christchurch with a third stage currently under construction. The phased delivery of the project allowed CoolTranz to continue operations with minimal disruption. With an innovative approach to workplace design and dedication to creating a positive and productive work environment, the client's commitment to excellence has resulted in a truly exceptional facility that sets a new standard for industrial workplaces.
Stage 1: A 1700m² cool storage distribution center featuring eight loading docks, each equipped with sectional insulated doors, inflatable dock seals, and hydraulic dock levellers.
Stage 2: A purpose-built office building designed to prioritize comfort and functionality for staff and truck drivers. Stage 2 was constructed while working in a live environment so maintaining a safe work environment was paramount. This stage incorporated custom and architecturally designed elements including:
Fully tiled showers and bathrooms.
Hand crafted vanities.
Custom louver system.
Rendered concrete plaster finish.
Expertly crafted kitchen and recreation areas.
A steel art wall depicting the journey of CoolTranz in the design.
Stage 3: A fuel depot that is currently under construction.
Challenges Overcome:
Logistical Coordination: Coordinating the delivery of internationally sourced materials required careful planning and mitigation strategies to ensure timely completion.
Live Environment: Maintaining a safe working environment was paramount. Procore facilitated effective tracking and reporting of safety incidents and hazards.
Tools and Technologies:
Procore: This construction management software provided a platform for communication, collaboration, managing financials, invoices, and design coordination.
Last Planner System: This project management method facilitated collaborative task planning between trade contractors, project managers, and stakeholders, ensuring clear workflows, accountability, and improved project delivery.
Project Delivery Method:
Stage 1: 1700m2 Coolstore warehouse and truck wash, completed December 2023
Stage 2: 433m2 Office block, completed in October 2024
Stage 3 : Fuel depot, currently under construction
Conclusion:
This project is a testament to our collaborative approach, efficient project management practices, and commitment to client satisfaction. By combining innovative tools, teamwork, and meticulous design, we delivered a high-quality facility that exceeds CoolTranz's expectations and paves the way for their future expansion.